Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

NESO hits Gate 2 grid offers milestone

Nordex bags 155MW haul in Europe

Crown Estate returns Morgan site to market

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    Crown Estate returns Morgan site to market

    June 8, 2026

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026
  • Onshore Wind

    Nordex bags 155MW haul in Europe

    June 9, 2026

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home»Offshore Wind
Offshore Wind

Judge rejects NY lease delay

Lawsuit will now continue in a District of Colombia federal court
EBSBy EBSFebruary 17, 20172 Mins Read
Share LinkedIn Facebook Twitter Bluesky Reddit Copy Link Email
NY plans offshore strategy

A US federal judge has refused to delay execution of the lease for the 1GW New York offshore wind area.

Statoil won the site at an auction in December, however, several fisheries organizations claim offshore wind development will harm the industry and have asked the court to block the sale.

The plaintiffs requested a preliminary injunction to delay the lease transfer until the full case has been decided.

Judge Tanya Chutkan this week denied the motion, citing plaintiffs’ failure to show “that the purported injury is certain, great, actual, imminent and beyond remediation”.

The Bureau of Ocean Energy Management had delayed the lease transfer until the motion was dealt with.

Following the court ruling the agency is now “working with Statoil on the next steps to execute the New York offshore wind commercial lease,” BOEM spokesperson Tracey Moriarty told reNEWS.

In the meantime, the lawsuit will continue in a District of Colombia federal court.

The plaintiffs claim the environmental analyses prepared by BOEM were defective, and in violation of the agency’s statutory and regulatory requirements, including that it failed to analyse the actual construction and operation of a wind project and further failed to consider other potential locations.

Image: Long Island (Wikimedia Commons)



Related Stories

Judge rejects US Wind permit review case

December 16, 2025

BOEM wraps up New York Bight review

October 22, 2024

BOEM cancels Gulf of Mexico auction

July 29, 2024
Advertisement

Latest News

NESO hits Gate 2 grid offers milestone

June 10, 2026

Nordex bags 155MW haul in Europe

June 9, 2026

Crown Estate returns Morgan site to market

June 8, 2026

PODCAST: Is UK offshore wind back on track?

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}