Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

NESO hits Gate 2 grid offers milestone

Nordex bags 155MW haul in Europe

Crown Estate returns Morgan site to market

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    Crown Estate returns Morgan site to market

    June 8, 2026

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026
  • Onshore Wind

    Nordex bags 155MW haul in Europe

    June 9, 2026

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home»Onshore Wind
Onshore Wind

Michigan OKs Pine River

Regulators approves Invenergy's 161.3MW wind farm in US state
EBSBy EBSDecember 29, 20161 Min Read
Share LinkedIn Facebook Twitter Bluesky Reddit Copy Link Email
Invenergy eyes Nebraska giant

Michigan regulators have given a green light to Invenergy’s 161.3MW Pine River wind farm in Gratiot and Isabella counties.

The state Public Service Commission has voted to approve a build-transfer contract with utility DTE Electric.

DTE selected the 65-turbine Invenergy project from four proposals submitted to a competitive request for proposals.

“The contract reflects lower costs to customers than originally anticipated and includes the benefit of the federal production tax credit (PTC),” said the commission.

The estimated installed cost of $1615 per kilowatt is significantly lower than the $2116 per kW assumed within DTE’s approved 2008 Amended Renewable Energy Plan, according to regulatory filings.

The developer is expected to use ‘safe harbour’ provisions to ensure the project qualifies for 100% of the PTC.

Invenergy plans to start commercial operation by the end of 2018.

After the construction is completed, DTE Energy will take over ownership of the Pine River wind farm.

Image: Invenergy



Americas Onshore Wind USA

Related Stories

SSE powers up 101MW Yellow River project

October 8, 2025

Invenergy pledges £14m to East Ayrshire

August 19, 2025

SSE wraps up Yellow River turbine installation

June 14, 2024
Advertisement

Latest News

NESO hits Gate 2 grid offers milestone

June 10, 2026

Nordex bags 155MW haul in Europe

June 9, 2026

Crown Estate returns Morgan site to market

June 8, 2026

PODCAST: Is UK offshore wind back on track?

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}