Bladt Industries has shipped the last five transition pieces for the 385MW Arkona offshore wind farm in the German Baltic Sea.
The structures have been transported from Aalborg to Sassnitz for installation at the project site 35km north-east of Rügen island.
Bladt fabricated a total of 60 transition pieces, including electrical design, for the project.
Eon and Statoil are jointly developing the €1.2bn project, which will consist of 60 Siemens Gamesa 6.4MW turbines.
Image: Eon/Markus Nitschke