Vestas has secured three wind turbine orders totalling 117MW in Germany as part of its second-quarter intake.
The company said the orders include a 31MW Nienwohlde project for BVNON Dienstleistungs- und Projektentwicklungs GmbH.
It added that a 50MW Vogelsberg project has been agreed with Boreas Energy alongside a 36MW Münk Arbach project for ENP Neue Energien GmbH.
The Nienwohlde project will use five V162-6.2MW turbines with a 25-year AOM 4000 service agreement.
The Vogelsberg project will deploy seven V172-7.2MW turbines under a 20-year AOM 4000 service agreement.
The Münk Arbach project will use six V150-6MW turbines with a 20-year AOM 5000 service agreement.
Delivery for the Nienwohlde and Vogelsberg projects is planned to begin in the second quarter of 2027 with commissioning scheduled for the fourth quarter of 2027.
Delivery for the Münk Arbach project is planned to begin in the third quarter of 2027 with commissioning scheduled for the second quarter of 2028.