Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » TenneT moves transformers to Maasvlakte station
Offshore Wind

TenneT moves transformers to Maasvlakte station

Web EditorBy Web EditorApril 20, 20262 Mins Read
TenneT moves transformers to Maasvlakte station

TenneT has completed the transport of the first three transformers to its 2GW converter station at Maasvlakte in Rotterdam.

The company said the units, each weighing up to 400 tonnes and standing over seven metres tall, were moved approximately 5.5 kilometres from the container terminal to the site on Dardanellenstraat during the night of April 18.

Advertisement

TenneT added that the remaining four transformers, part of a shipment of seven that arrived from Liverpool in February, will be transported in May.

The transformers will process electricity from the IJmuiden Ver Beta and Gamma offshore wind farms at the converter station currently under construction.

The operation required complex logistics, including crossing a railway line with transport combinations approximately 20 metres long and weighing up to 400 tonnes.

The transformers form part of TenneT’s 2GW connections that convert offshore direct current electricity into 380kV alternating current for transmission on the national grid.

The installations use a new generation of high-voltage direct current technology operating at higher voltage levels with additional requirements for cooling and noise reduction.

At the site, the transformers have been placed in their final positions and will undergo further assembly and connection over several weeks, including filling with more than 100,000 litres of insulation and cooling oil per unit.

Commissioning of the installations will take place in phases over the coming years.

Electricity from the system will be supplied to the Rotterdam port area via the Amaliahaven high-voltage substation and support applications including large-scale hydrogen production.

converter station Maasvlakte Offshore Wind Tennet
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleWindEurope 2026: ONYX launches blade monitor
Next Article Solar ‘leads global energy supply growth’

Related News

TenneT Germany invests record €10bn

March 9, 2026

Seatrium, GE start work on Nederwiek 2 platform

February 6, 2026

Berlin buys 25.1% of TenneT Germany

February 3, 2026
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Pembroke Port
  • Ørsted
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}