Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » National Grid advances North Wales grid upgrade
Grid

National Grid advances North Wales grid upgrade

Web EditorBy Web EditorJanuary 21, 20262 Mins Read
Ofgem approves hybrid interconnector pilots

National Grid has had four planning applications validated for proposals to reinforce and refurbish the electricity network between Pentir and Trawsfynydd in North Wales.

The applications were submitted in early December to Gwynedd Council and Eryri National Park Authority and have now passed the initial checks confirming they are complete, said the company.

Advertisement

The upgrades form part of the Great Grid Upgrade and are required to meet rising electricity demand, added the developer.

National Grid stated that the work will support Wales’ clean power and energy security goals and help lower constraint costs.

The plans cover new and replacement equipment at the existing substation sites at Pentir and Trawsfynydd, 5.8km of replacement underground cables beneath the Glaslyn Estuary at Porthmadog, and construction of a new substation south of Bryncir.

The applications follow public information events in May and 28-day statutory pre-application consultations held in September.

National Grid anticipates decisions early next year.

Subject to approval, construction is due to begin in summer 2026 with the project scheduled to be fully operational in 2030.

John Lamb, director for Pentir to Trawsfynydd, said: “We are pleased to have reached a significant milestone for our Pentir to Trawsfynydd project.

“We need to reinforce and refurbish the existing electricity network between Pentir and Trawsfynydd to meet rising electricity demand and allow new sources of cleaner, home-grown energy from more affordable sources to reach homes and businesses. This will help to enable a clean energy future for Wales, make our energy supply more secure, independent and deliver long-term benefits to bill payers.”

National Grid upgrade Wales
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleDNV supports $325m financing for Chile renewables
Next Article Enviromena wins consent for Kent solar

Related News

National Grid energises second Dinorwig circuit

April 7, 2026

First new Dinorwig cables power up

March 10, 2025

CIP to take minority stake in Bute Energy

February 26, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}