Seaway7 has installed the last of 87 monopiles at SSE, Equinor and Vargronn’s 1.2MW Dogger Bank C wind farm off north-east England.
The milestone means the construction company has hammered in a total of 277 bases across all three phases of the 3.6GW North Sea complex.
Advertisement
“Our teams have delivered strong predictable performance, enabling efficient cycle times while maintaining safety and quality throughout the offshore campaigns,” said Seaway7.
Heavy lift vessel Seaway Strashnov has been deployed at Dogger Bank C since April.
Fleet mate Alfa Lift will remain on site until later this year to install around 30 remaining transition pieces to conclude the foundations works.