Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Dutch approve IJmuiden Ver Beta delay to 2032
Offshore Wind

Dutch approve IJmuiden Ver Beta delay to 2032

Stephen DunneBy Stephen DunneAugust 8, 20253 Mins Read
HKZ turbine installation wraps up

The Dutch government has amended the permit for the 2GW IJmuiden Ver Beta offshore wind farm to allow half of the capacity to be built in 2032.

The scheme, awarded in June 2024 to Zeevonk, a joint venture between Vattenfall and Copenhagen Infrastructure Partners, was originally due for full completion by the end of 2029 alongside a 1GW electrolyser at Maasvlakte and a 50MWp offshore solar array.

Advertisement

Minister for climate and green growth Sophie Hermans stated in a letter to cabinet that the delay to the Delta Rhine Corridor hydrogen pipeline to 2032 meant the project was no longer financially viable under its original terms.

The pipeline is designed to transport green hydrogen from Maasvlakte to customers in the Netherlands, Belgium and Germany, but without it, Zeevonk would face a limited market and major revenue shortfalls.

Under the revised consent, 1GW will still be delivered in 2029, with the second 1GW to follow in 2032, broadly matching the new pipeline completion date. The change will count half of the project towards the Netherlands’ 2030 climate target, while avoiding a complete permit re-tender.

The minimum mandatory system integration capacity, such as electrolysers, has been reduced to 500MW, with commissioning scheduled for 2033 when the Delta Rhine Corridor is operational.

Zeevonk’s total permit payment has been cut from €800m to €400m. The developer will pay €20m annually for the first two years, pause payments for several years, then increase instalments after the wind farm is commissioned, with the highest amounts due in the final years of the 40-year term, according to Hermans.

The offshore solar requirement has been amended to an “innovative” 6MWp pilot by 2028, with expansion to 50MWp if technically and financially viable. This smaller project is due earlier than under the original permit.

The government said the phasing would have “considerable financial consequences” for grid operator TenneT, which has contracts in place for the 21GW offshore wind roadmap and will now need new agreements for the delayed capacity. These additional costs, if approved by regulator ACM, will be recovered through network tariffs.

Hermans said the changes followed extensive discussions with Zeevonk and an independent review by KPMG, which found the amendments reasonable and not overcompensating the developer for the Delta Rhine Corridor delay.

Without the revised terms, Hermans said Zeevonk would likely have been unable to build the project, triggering a permit revocation, a lengthy re-tender process and the loss of almost the entire financial bid.

She added that in the current market, interest from other developers would be limited, risking greater delays and higher costs to the state and TenneT.

CIP Europe IJmuiden Ver Beta Netherlands Offshore Wind Vattenfall
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleEarnings dip in EnBW’s green business
Next Article Gresham hits 1GW milestone for UK BESS

Related News

TKF lands Zeevonk cable contract

May 11, 2026

First steel cut for IJmuiden Ver Beta substation jacket

September 5, 2025

Vattenfall-CIP, SSE win 4GW Dutch offshore wind tender

June 11, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}