Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Statkraft seeks licence for €340m hydro upgrade
Hydro

Statkraft seeks licence for €340m hydro upgrade

reNEWS EditorialBy reNEWS EditorialMay 2, 20253 Mins Read
Statkraft names new chief executive

Statkraft is seeking a licence to upgrade the Nore hydropower plants in Norway with a 4 billion NOK (€340m) budget.

The new power plant will be able to deliver more electricity when needed and contribute to more stable prices, the company said.

Advertisement

The Nore plants consist of the Nore 1 and Nore 2 power plants.

Nore 1 was completed in 1928, while Nore 2 began production in 1946. The facilities are located on the Numedalslågen river in Norway.

President and chief executive Birgitte Ringstad Vartdal (pictured) said: “In the coming years, Statkraft will build the next-generation hydropower system, and we will start five major upgrades by 2030.

“The licence application for upgrading and expanding the Nore plants is an important step in that direction.”

Nore 1 produces 70 times more power than the Hammeren power plant in Maridalen, which supplied the Norwegian capital from 1900, and was built to cover all of Oslo’s electricity needs.

Vartdal added: “When the first Nore plant was built, it was the largest in the country and produced one-fifth of all electricity in Norway.

“The power plant was also a catalyst for the industrialisation of Oslo. And now, 100 years later, we will ensure that it supplies the Norwegian society with electricity for another 100 years.”

Statkraft is considering two options for the upgrade. The preferred option is to combine the plants into one new power plant inside the mountain, but there is also an alternative where the two power plants are moved into the mountain from where they are currently located.

The first option will nearly double the capacity from 274MW to 500MW and increase electricity production by approximately 200GWh to about 1700GWh.

The alternative option will increase the combined capacity by 65MW and boost production by around 150GWh.

Statkraft project maanger Hanne Kristin Ommedal said: “In the power system of the future, there will be a great need to regulate production to deliver more electricity in a short amount of time.

“Therefore, we are constantly looking for opportunities to increase the capacity of our plants.

“More capacity can help reduce price peaks, as more and more unregulated renewable power enters the power mix.

“The new Nore power plant will be important both for the region and for Norway.”

The licence application will now be processed by the Norwegian Water Resources and Energy Directorate (NVE), and as part of this, a hearing process will be conducted.

The Ministry of Energy will decide on a possible licence and its conditions.

Birgitte Ringstad Vartdal Hydro hydropower licence Ministry of Energy Nore Nore 1 Nore 2 NVE Renewable energy news Statkraft
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article4.1GW Berwick Bank ‘key for climate fight’
Next Article £3.4m boost for Scottish hydrogen

Related News

Statkraft narrows focus to boost core assets

June 18, 2025

Statkraft to operate in fewer countries

October 23, 2024

Statkraft closes Enerfin acquisition

May 23, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}