Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Cable production starts for 2GW TenneT platforms
Grid

Cable production starts for 2GW TenneT platforms

Eleanore RobinsonBy Eleanore RobinsonMay 31, 20243 Mins Read
Cable production starts for 2GW TenneT platforms

TenneT has announced the start of production at LS Cable in Donghae, South Korea of new cables that can transmit up to 2GW of offshore wind capacity.  

The new 525kV cables make it possible to transmit 2GW of direct current over long distances with low losses, TenneT said.

Advertisement

Up to now, 320 kV cables have been used for offshore grid connections, for example in TenneT’s 900MW projects.

The start of cable production is part of the framework agreement that TenneT concluded with the consortium consisting of the Jan De Nul Group, LS Cable & Systems and Denys in May 2023.

The contract covers the production and installation of four 525kV DC cable systems for the TenneT grid connection projects in the North Sea.

The first DC cables produced by the South Korean cable manufacturer LS Cable are intended for the BalWin4 and LanWin1 grid connection projects.

In addition to a positive and negative pole, an additional cable – a so-called metallic return conductor – will be laid for both grid connections in future, which will ensure that electricity can continue to flow in the event of maintenance or repair work.

The three cables will be supplemented by an additional communication cable.

A total of 1,650 kilometres of cable will be produced for the BalWin4 and LanWin1 projects (route length per project: 275 kilometres, of which 165 kilometres are submarine cables and 110 kilometres are land cables).

The inner conductor is made of copper, which makes the cables really heavy.

The submarine cables alone weigh around 76 kilograms per metre. The total weight for the submarine cable (plus/minus pole) is therefore around 25,000 tonnes per project – a logistical challenge.

Production of the cables will be completed in 2028.

Cable laying at sea is expected to begin in the second half of 2026.

The Jan De Nul Group will use the extra-large cable-laying vessel ‘Fleeming Jenkin’, which was specially designed and ordered for the transport and laying of the 525 kV DC cables on the seabed.

The construction of the land cable is also scheduled to start in the second half of 2026 by the construction company Denys, with work being carried out as usual using the open trench method with a cable trench and the closed trench method using horizontal drilling.

These will be used to cross bodies of water and existing infrastructure such as railway lines, dykes, roads and the like.

BalWin4 is scheduled to go into operation in 2029, LanWin1 in 2030.

BalWin 4 Cables LanWin1 LS Cable South Korea Tennet
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleLabour outlines Great British Energy vision
Next Article European Energy swings to Q1 loss

Related News

Asso Subsea wins TenneT cable-laying gig

July 29, 2025

Jan De Nul consortium bags 1000km wire gigs

December 6, 2023

Jan de Nul installs first HK West Alpha sea cable for TenneT

January 25, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}