PGE and Orsted have now finalised all agreements for vessel fleets to install wind turbines at the 1500MW Baltica 2 offshore wind project in Poland.
The partners tendered the installation as two phases with each phase’s contractor selected in separate tenders.
The second batch of turbines will be installed by Cadeler, and with this agreement PGE and Orsted finalised the contracts for the installation of the turbines.
In early January, the contract for the installation of the first batch of turbines was awarded to Fred Olsen Windcarrier.
PGE and Orsted have already contracted all the necessary components for the Baltica 2 offshore wind farm, as well as signed contracts for the installation of foundations, turbines and cables.
The partners also selected the general contractor for the onshore connection infrastructure.
They already obtained all the necessary construction permits.
The last step before the construction begins will be the final investment decision (FID).
Baltica 2 is one of two stages of the Baltica Offshore Wind Farm – next to Baltica 3.
PGE and Orsted plan to deliver Baltica 2’s 1.5GW capacity by the end of 2027 and Baltica 3’s 1GW capacity by 2030.
Baltica 2 and Baltica 3 will create the Baltica Offshore Wind Farm with a capacity of 2.5GW.