French offshore wind farm Fecamp has reached its latest milestone with the installation of half of its turbines.
As of 15 January, 37 of the 71 units have been installed at the site of the 498MW offshore wind farm, 13km off the Normandy coast.
Advertisement
Fecamp offshore wind farm has been producing and injecting electricity into the grid since the summer of 2023 and will soon reach an injection capacity of nearly 250MW.
To ensure the smooth running of the installation of the turbines, the site mobilizes more than 1000 people on a daily basis spread between Le Havre, Cherbourg and Fecamp.
Fecamp’s first gravity base foundation was installed in August 2022.