Ilmatar’s Västervik and Isokeidas wind farms are generating renewable energy with 14 turbines, totalling nearly 87MW of nominal capacity.
Construction of both projects began in July 2022, following the investment decisions for the wind farms.
With the Västervik and Isokeidas farms, Ilmatar has started commercial production at six renewable energy production sites in 2023 so far.
These wind and solar power farms will remain in Ilmatar’s ownership throughout their entire lifecycle, following the company’s strategy.
Petri Ainonen, Ilmatar’s director for construction, said: “Completing the construction of Västervik and Isokeidas ahead of schedule was a success, and the work complemented the earlier completion of Jäkäläkangas wind farm.
“The challenging wind conditions in late summer and early autumn added their own touch to the installation of wind turbines in Isokeidas and Västervik.
“However, active work planning and fitting the work into suitable wind windows enabled us to overcome these challenges.”
AIP Management participated as a financer in Isokeidas, Västervik, Jäkäläkangas and Palma wind farms that have all been taken into commercial operation during 2023.
The total capacity of the four wind farms is 131.8MW.