Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Crosswind installs final HKN turbine
Offshore Wind

Crosswind installs final HKN turbine

Eleanore RobinsonBy Eleanore RobinsonOctober 20, 20232 Mins Read
Crosswind installs final HKN turbine

Crosswind has announced that the 69th and final wind turbine has been installed at the 759MW Hollandse Kust Noord offshore wind farm in the Netherlands.

The wind park remains on track for completion by the end of this year, with final testing and commissioning works set to continue over the next few weeks.

Advertisement

When fully operational, CrossWind’s 69 turbines will operate in 11MW power mode, generating at least 3.3TWh per year.

This annual green electricity production will fulfil some 2.8% of the electricity demand in the Netherlands and is equivalent to the energy consumption of approximately 1 million households.

The project in the North Sea also comprises floating offshore solar and a hydrogen plant. 

Tjalling de Bruin, chief executive and project director at CrossWind, a JV between Shell and Eneco, said: “I am delighted to see the installation of our final turbine.

“We could not have done this without our colleagues, suppliers and partners who have worked tirelessly and – perhaps most importantly – safely to achieve this major milestone.

“A number of the turbines are already generating clean, green electricity for the Dutch grid, accelerating the energy transition.”

Van Oord started installing the foundations of the offshore wind park in October 2022. 

Roeland Ris, project director at Van Oord, added: “The installation of the 69th and final wind turbine in the wind park is a magnificent achievement.

“Completing the safe installation of this offshore wind park in this time frame is something that everyone involved in the project can be very proud of.

“We are pleased to collaborate with Shell and Eneco on this prestigious project and look forward to working together again on the construction of Ecowende’s offshore wind park at Hollandse Kust (west) lot VI.”

CrossWind Eneco HKN Netherlands Shell Siemens Gamesa Van Oord
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleWelsh tidal stream site opens for business
Next Article DEME JV to prep seabed at Greater Changhua

Related News

HKN becomes operational

December 20, 2023

Siemens Gamesa, CrossWind sign HKN turbine deal

February 11, 2021

Shell, Eneco join Hollandse Kust Noord tender

May 7, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Oceantic Network
  • LSP
    LSP Renewables
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}