Vestas has received a firm 147MW order from SR Energy for turbines for the Horshaga wind project in Uppvidinge municipality, southern Sweden.
The order consists of 20 V162-6.2MW and five V150-4.5MW machines and includes supply, delivery, and commissioning of the units.
Turbine delivery is expected to begin in the first quarter of 2025 with commissioning scheduled for completion in the first quarter of 2026.
Upon completion, Vestas will service the machines under a 35-year agreement.
“We are proud to realise the Horshaga project together with our long-term customer SR Energy,” said vice president sales for northern and central Europe at Vestas Anna Schlasberg Wachtmeister.
“We are grateful for the continuous trust in Vestas for the delivery and services to SR Energy’s projects.
“This order underlines our shared focus on sustainable investments into the renewable energy transition in Sweden.”
SR Energy chief executive Peter Zachrisson added: “We very much look forward to realising another 147MW of renewable energy for the Swedish electricity system.
“Wind park Horshaga will provide a welcome addition of renewable energy in southern Sweden and enable regional development and industrial transformation.
“Technical innovation, sustainability at all levels and reliable delivery are qualities that we value in Vestas as a business partner.”