Cable-laying work at Vineyard Wind’s 800MW offshore wind farm is about to get under way in the US.
Jan de Nul’s vessel Issac Netwton will be conducting operations on the inter-array wires and will remain on-site until early October.
Advertisement
The work will begin with cable lines five and six.
The C-Pioneer will be acting as a stationary support vessel, supporting wire-pulling activities for the lines.
The trenching support vessel Adhemar de Saint-Venant will be performing cable trenching and burial works.
The F/V Seafarer will be operating as a safety vessel to monitor traffic and facilitate safe movement of fishing boats, recreational craft, or other transiting ships around the work sites and project vessels.