Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Speeding up UK grid buildout a ‘game changer’
Grid

Speeding up UK grid buildout a ‘game changer’

Eleanore RobinsonBy Eleanore RobinsonAugust 4, 20234 Mins Read
Fugro maps German path for TenneT

The renewables industry has welcomed UK Electricity Networks Commissioner Nick Winser’s report, saying halving the delivery times for transmission projects to seven years would be a “game changer”.

Findings of the nine-month review were presented to UK Energy Secretary Grant Shapps earlier today.

Advertisement

They set out a series of recommendations to streamline the delivery of new grid infrastructure and implement a more strategic approach to deployment to keep pace with the acceleration of renewable generation.

RWE UK country chair Tom Glover said: “Nick Winser’s recommendations address a major national issue with an equal scale of ambition to halve the speed of grid connections from around 14 years to just seven.

“This would be a game changer for the industry and the country, but needs a step-change in attitude focused on planning more strategically and long-term, plus an invigorated sense of urgency to adopt and deliver proposals quickly.

“Grid is widely accepted as the single biggest blocker to the deployment of new, low carbon power, and risks delays to investment and net zero.

“Connection delays of up to six years are already impacting RWE’s development pipeline.

“As a leading provider of UK electricity and energy security, we can do our bit by speeding-up deployment, but need to be able to plug in faster to get that power to UK homes.”

Trade group Energy UK’s deputy director Adam Berman added cutting the time to plan and build network infrastructure is arguably the most pressing challenge facing the energy transition.

He said: “Hitting our ambitious targets for the expansion of clean domestic energy that will cut bills and emissions while strengthening our energy security depends on being able to connect projects to the network much quicker than is currently the case for many of them.     
 
“So we welcome Nick Winser’s recommendations, particularly the focus on strategic network planning as well as supply chain development and skills, and encourage the government to respond to these recommendations with urgency and ambition.
 
“Alongside the joint Ofgem and DESNZ Connections Action Plan anticipated later this year, the government’s response to this report must represent a transformative change to the way we develop net zero infrastructure.”

Energy Secretary Grant Shapps has said he will consider the report’s findings before setting out an action plan later this year.

RenewableUK added it was pleased to see the “timely” report put forward a series of constructive measures to speed up the pace at which the UK builds vital new grid infrastructure.

Chief executive Dan McGrail said: “These recommendations will benefit billpayers across the country by ensuring that we maximise  the vast quantities of cheap, clean power we’re generating from renewables, and that we can get it to British homes and businesses more efficiently.

“The UK has reached a turning point where delaying new grid is not in the best interests of consumers, as they need to be able to access electricity at the lowest cost more easily.

“This report shows that removing constraints and bottlenecks from the grid as a matter of urgency will provide the best value for money for billpayers.

“It sets out a range of proposals for a strategic long-term plan for network development which will be essential to meet our net zero goals.”

Octopus Energy Generation chief executive Zoisa North-Bond added: “Power from renewables is currently cheaper than power from fossil fuels, but grid connection wait times remain a national scandal. It’s brilliant to see these recommendations to streamline the UK’s grid system and we hope they can be rolled out quickly.

“The UK is on the cusp of a massive decarbonisation opportunity, to build and connect more green energy and deliver cheaper, cleaner energy to people as a result. Timing is of the essence – the need to bring down bills and boost our energy security couldn’t be more urgent.”

Energy UK Grid Offshore Wind RenewableUK RWE Transmission UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleUK ‘needs to halve transmission delivery times’
Next Article Shapps ‘to consider’ Winser report recommendations

Related News

System operator outlines £58bn UK grid plan

March 19, 2024

‘Scotland lacks grid capacity’

February 15, 2024

UK offshore wind champion calls for grid upgrade

April 5, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • Full Circle Wind Services
  • EDF
    EDF
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}