Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Heerema installs Baltic Eagle substation topside
Offshore Wind

Heerema installs Baltic Eagle substation topside

SaraBy SaraFebruary 23, 20232 Mins Read
Heerema installs Baltic Eagle substation topside

Heerema Marine Contractors has installed the offshore substation (OSS) topside for the Baltic Eagle offshore wind project, off Germany, using the installation vessel Thialf.

It follows the installation of the jacket foundation in October 2022.

Advertisement

The role of the OSS is to collect the electricity generated by the 476MW offshore wind farm’s turbines and transform the supply voltage before feeding it into the onshore power grid at the Lubmin grid interconnection point.

The installation involved the heaviest lifting operation for the Baltic Eagle project with a total estimated net weight of around 4200 tonnes.

Iberdrola has now started the offshore phase to make the OSS ready for energisation.

This will be followed by the installation of the monopiles to which the wind turbines are attached with transition pieces.

The monopiles have been manufactured by the regional company EEW SPC, in Rostock.

Once the wind farm is connected to the grid, the electricity generated by its wind turbines will be delivered via inter-array cables to the offshore substation where it is then transformed from 66kV to 220kV and transmitted via two high-voltage subsea cables across the 90 km distance to the landing point at Lubmin into the 50Hertz transmission grid.

The 220 kV submarine cables were already laid in 2021 and 2022 and deposited on the seabed at a safe distance from the platform position.

The next step will be to move the two cable ends into the transformer platform in the second quarter of this year.

In May 2021, Iberdrola and 50Hertz signed an agreement to cooperate on the construction, installation and commissioning of the OSS for Baltic Eagle offshore wind farm.

Iemants-Fabricom was responsible for the manufacturing of all structural elements of the substation, the marine contractor Heerema for transportation and installation, and Siemens Gas and Power for the delivery of all main electrical equipment for Iberdrola’s low-voltage part of the OSS.

Iris Stempfle, Managing Director of the Offshore Division and Deputy CEO of Iberdrola Deutschland, said: “The offshore substation is a key piece of technology for supplying sustainable energy to hundreds of thousands of households and for the decarbonisation of German industry.”

Baltic Eagle Heerema Iberdrola Offshore Wind
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleDIF snaps up UK solar-storage portfolio
Next Article Siemens Gamesa installs 15MW prototype

Related News

Iberdrola installs all Baltic Eagle turbines

October 16, 2024

First turbine goes up at Baltic Eagle

May 9, 2024

Iberdrola, Vestas select Roenne for Baltic Eagle marshalling

August 24, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}