Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Orsted toasts installation milestone at Hornsea 2
Offshore Wind

Orsted toasts installation milestone at Hornsea 2

SaraBy SaraOctober 21, 20212 Mins Read
Heerema wraps up Hornsea 2 substation jackets job

Orsted has completed installation of all 165 foundations and the project’s offshore substation at its 1.4GW Hornsea 2 wind farm, 89km off the UK North Sea coast.

The installation of the monopile foundations means that the project is ready for the final third of wind turbines to be installed, ahead of the wind farm coming online in 2022.

Advertisement

Hornsea 2’s offshore substation is the world’s largest alternating current version, weighing around 8000 tonnes. It was safely lifted into position by the vessel Sleipnir.

Also onsite is the reactive compensation station which will be lifted into place in the coming days.

Finally, the project has also recently laid all 390 km of export cable needed to take the electricity generated from the wind farm to the onshore substation and ultimately the National Grid.

Spanning an offshore area of 462 sq km, Hornsea 2 will be the world’s largest wind farm when it goes into operation.

Hornsea 2 programme director Patrick Harnett, at Orsted, said: “These twin milestones, together with the completion of our export cable circuits, mark the culmination of a truly monumental scope of work involving multiple teams from numerous companies working together in the face of some significant challenges over the last 18 months.

“These are very complex operations and major engineering achievements, delivered thanks to the dedication, professionalism and positivity of the whole project team and we are all delighted that we have completed these significant milestones along the road to having the wind farm fully up and running in 2022.”

When Hornsea 2 is operational Orsted will be supplying over 7% of Britain’s electricity.

Heerema Hornsea 2 Offshore Wind Orsted
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article‘Green hydrogen key to hitting climate target’
Next Article Cypress Creek closes 270MW Texas solar financing

Related News

Orsted takes FID on 2.9GW Hornsea 3

December 20, 2023

Orsted awards Hornsea cable landing works contract

August 25, 2023

NKT wins Hornsea 3 export cable supply deal

March 31, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}