The two topsides for the offshore substation and reactive compensation station (RCS) for the 1400MW Hornsea 2 offshore wind farm have been loaded out in Singapore, ahead of transport to Europe.
The units have been moved on to Guangzhou Salvage’s Hua Hai Long vessel at Sembawang, Singapore.
Advertisement
They were manufactured by Sembcorp Marine.
Jacket foundations for the two structures have already been installed in the North Sea.
Heerema vessel Sleipnir completed installation of the jacket for the RCS in October last year, with the foundation for the substation having been installed a month earlier.
Hornsea 2 will feature 165 Siemens Gamesa 8.0-167 turbines and is expected online next year.