Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Greenlink Interconnector wins first consent
Grid

Greenlink Interconnector wins first consent

reNEWS EditorialBy reNEWS EditorialJuly 15, 20202 Mins Read
DeepOcean offers wire fix package

Pembrokeshire Coast National Park Authority has awarded the proposed 500MW Ireland-Wales Greenlink Interconnector the first of several consents the project needs to secure before it can start construction.

The planning approval covers a portion of the project’s onshore works in Wales comprising underground cables and associated works from the subsea link’s landfall site at Freshwater West to the boundary with Pembrokeshire County Council.

Advertisement

This marks the first step in a series of planning consents required for the 200km subsea and underground electricity interconnector, which will link the power markets in Ireland and Great Britain.

Separate planning applications have been submitted to Pembrokeshire County Council for the onward installation of cables to the substation at Pembroke Power Station and for development of a converter station.

Pembrokeshire County Council is scheduled to consider these two applications at its planning committee on 28 July.

Greenlink Interconnector Limited’s chief executive Nigel Beresford said the project development team was “delighted” about the decision by members of the Pembrokeshire Coast National Park Authority Development Management Committee.

He added: “From the outset we have placed the feedback received from all key stakeholders, including the local community, at the heart of our design decisions to ensure that the Greenlink interconnector is well designed and a good neighbour to the residents living near it.”

In Pembrokeshire the Greenlink interconnector comprises a subsea cable intended to come ashore under the beach and dunes at Freshwater West and continuing underground to a new converter station located near to the existing Pembroke substation.

The marine planning applications in both Wales and Ireland were submitted towards the end of 2019 and the application for onshore works in Ireland is currently being prepared. The project is expected to have a three-year construction programme.

Greenlink said the interconnector was one of Europe’s most important energy infrastructure projects and would bring benefits on both sides of the Irish Sea for energy security, regional investment, jobs and the cost-effective integration of low carbon energy.

Greenlink
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleCOVID-19: Sembcorp makes $192m 1H loss
Next Article Nordex books 888MW in Q2 orders

Related News

Partners Group takes full ownership of Greenlink project

May 12, 2021

Greenlink clears Welsh licence hurdle

March 3, 2021

Greenlink gains onshore planning approvals in Wales

July 28, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • LSP
    LSP Renewables
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}