Cable-laying vessel NKT Victoria has installed the first HVDC cables in the Moray Firth as part of Scottish and Southern Electricity Networks’ £1.1bn Caithness-Moray transmission project, which will transport renewable electricity from the north of Scotland to areas of demand in the south.
The vessel (pictured) completed its first campaign from Noss Head in Caithness to the midpoint of the cable route this week.
It has now returned to Sweden to reload the remaining cable to be laid from Portgordon in Moray to the end of the previously laid cable later this month.
SSEN lead project manager Brian Mitchell said: “This is a major milestone for the Caithness-Moray project and I am delighted that the first cable laying campaign was completed on schedule.
“The vessel has now returned to Karlskrona in Sweden to load the remaining 56km of HVDC cable.
“A subsea joint will then be constructed to connect both sections of cable to complete the circuit.”
The Caithness-Moray project is on schedule for completion in 2018.
Image: NKT