The final transition piece for Vattenfall’s Danish Kriegers Flak has been loaded onto barge by Bladt Industries ready for transport.
The piece is due to be installed in Vattenfall’s 604MW project in the Danish Baltic Sea, Bladt said.
In total 432 cans have been rolled, welded, painted and outfitted during the last 12 months, according to the offshore steel manufacturer.
The weight of each transition piece is 158 tons in primary steel and has a height of 16.5m.
In addition, 48 tons of secondary steel, 1.8 tons paint, 3.4 tons of grout and 600 kg electrical cables is added to the weight of each transition pieces.
Blade Industries senior project manager Torben K Christensen said: “It has been a pleasure to work closely together with the team from Vattenfall.
“This project has clearly been executed with a common goal for the benefit of the project.”