The UK Supreme Court will soon rule on the long-running case between Eon and MT Hojgaard over historic grouting issues at the 174MW Robin Rigg offshore wind farm in the Solway Firth.
A decision is expected on 3 August. The court decided to hear an appeal from Eon in December 2015 despite having previously cleared contractor MT Hojgaard the previous month.
The Danish company set aside Dkr195m (€26m) as a special item in the 2015 accounts to offset potential losses related to the case.
Robin Rigg is one of several wind farms that suffered from the grout issue, which affects the join between monopile foundations and transition pieces.
Image: Robin Rigg offshore wind farm (Eon)