Dominion Energy has delivered first power at its 2600MW Coastal Virginia Offshore Wind array.
Dominion CEO Robert Blue said in a LinkedIn post: “This achievement marks another important step forward, adding much‑needed electricity to help meet the fastest‑growing power demand in the country.
Advertisement
“As additional turbines are installed, CVOW will continue delivering more power on the path to full completion early next year.”
CVOW completed monopile installation for the 176-turbine project in the autumn of 2025, and began installing turbines this year with its purpose-built jack-up Charybdis.
The project features three offshore substations, alongside the 176 Siemens Gamesa 14MW turbines.