All 31 turbines on monopile foundations have been commissioned at Northland Power’s 269MW Deutsche Bucht offshore wind farm in the German North Sea.
The wind farm has a total of 33 turbines. Installation of the 31 MHI Vestas 8.4MW turbines was completed by contractor Van Oord last August.
Advertisement
Grid connection is fully available, the company confirmed, adding that all the 31 turbines have been commissioned.
Final fabrication on the two mono bucket foundations is currently ongoing at Bladt Industries facilities in Lindoe, Denmark with a final operational deadline for all 33 turbines scheduled for the end of the year, said the company.
On 26 July, the project’s first turbine began delivering power to the German grid.