Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home»Offshore Wind
Offshore Wind

Dominion cuts costs off Virginia

Fred Olsen among bidders as pricetag comes down by $100m
EBSBy EBSApril 7, 20162 Mins Read
Share LinkedIn Facebook Twitter Bluesky Reddit Copy Link Email
All-clear for Virginia offshore demo

The price to build Dominion Power’s planned 12MW offshore wind project off Virginia has dropped by as much as $100m but the utility continues to hold off on a final investment decision over concerns about ratepayer impacts.

The US utility held a second round of bidding on the two-turbine demo after construction costs off Virginia Beach escalated to $400m, nearly double the initial estimate of $230m.

The latest figures total $300m to $380m, Dominion VP generation construction Mark Mitchell said in a conference call. “We expect to come in at the lower end of that range,” he said.

Dominion divided the project into four packages to try to lower costs. It received two bids for transportation and installation of foundations and turbines; one bid for design, manufacturing, transportation and installation of subsea cables; four bids for foundation fabrication; and one bid for onshore connection facilities.

The highest cost is for the marine component, which is the “most significant remaining uncertainty in the project”, he said.

Bids included a proposal from Fred Olsen Windcarrier using specialist jack-up vessel Brave Tern, which will install turbines at Deepwater Wind’s 30MW Block Island pilot project in Rhode Island later this year.

Dominion officials plan to meet in early May with the US Energy Department, which is contributing up to $51m, to discuss potential paths forward and timelines.

The demonstration scheme, dubbed VOWTAP, has a 31 May 2016 milestone deadline to receive the next DoE instalment. “We do feel we’ve largely met the requirements,” said Mitchell.

Project partners already have spent $25m with the lion’s share coming from Dominion and the DoE.

The utility expects to release another project update this summer and make a final decision on next steps by July. If all goes to plan it will then seek regulatory approval to pass on the cost to ratepayers.

The earliest possible in-service date is 2018, said Mitchell.

The Virginia demo comprises a pair of GE Haliade 150 6MW turbines on Keystone twisted jacket foundations 27 miles off Virginia Beach.

Mitchell called the merger between GE and Alstom “a positive” that did not create any impacts on project costs or forecasts.

The site lies next to Dominion’s 2GW commercial lease area, which is slated for staged development in 2020 to 2025. “We continue to meet all our requirements for the commercial lease and VOWTAP is the first step in that process,” said Mitchell.

Image: Dominion is planning to build off Virginia Beach (reNEWS)



Americas Offshore Wind USA

Related Stories

Dominion seeks 2.6GW Coastal Virginia approval

November 5, 2021

Dominion taps Siemens Gamesa for 2.6GW Virginia giant

January 7, 2020

Dominion, Dong form US team

July 10, 2017
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Pembroke Port
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}