Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Dublin approves new offshore wind policy plan
Offshore Wind

Dublin approves new offshore wind policy plan

Stephen DunneBy Stephen DunneMarch 10, 20233 Mins Read
Dublin launches offshore wind lease talks

The Irish government has approved a new development framework for the next phase of offshore wind.

Phase 2, which will follow from the current 4.4GW of Phase 1 sites bidding in the debut offshore wind auction, will be an “accelerated work programme which will focus on near term delivery based on technology with proven scalability in other jurisdictions”, according to Energy Department DECC.

Advertisement

The process will be plan-led “exclusively” procuring “a set volume of offshore wind capacity for development within individual Offshore Renewable Energy (ORE) Designated Areas”, as first revealed by subscriber-only reNEWS on 23 February.

Sites will be located off the south and south-east coast, with one 700MW project and two 350MW schemes in the mix, based on grid availability identified by transmission system operator Eirgrid.

A second offshore auction for development rights to the projects will launch by the end of 2023 and capacity is due online by 2030, according to Energy Department DECC led by Energy Minister Eamon Ryan (pictured).

“For the avoidance of doubt, all Phase 2 auctions will exclusively seek to procure offshore wind capacity located within ORE Designated Areas, including potential additional future auctions on the East or West coast should additional grid capacity be identified by EirGrid following completion of Phase 1,” said officials.

However, Wind Energy Ireland has warned the policy, published this morning, will undermine efforts to achieve the targets set for offshore wind energy in the Climate Action Plan.

WEI pointed out the plan contains of two major changes by introducing a requirement that all future offshore wind farms must be built in Designated Marine Areas which have yet to be identified and may not be for 18-24 months.

Second, it proposes that future offshore wind farms will not connect to points on land but to offshore substations to be designed and built by EirGrid, something never done by the company before.

Noel Cunniffe, CEO of Wind Energy Ireland, said: “This is a radical change in policy from Government that has created massive levels of uncertainty among international investors and the global supply-chain.  

“They are gambling that State agencies can identify Designated Marine Areas quickly. Unfortunately, our experience is that those agencies are grossly under-resourced and will struggle to deliver in time unless the right people with the right skills are put to work on it as soon as possible.

“Our members have been working for years to deliver the projects Ireland needs only for the rules to change, without warning, in the middle of the process. We are effectively being told to stop developing offshore wind energy and wait for further decisions at a point when we have no time to lose.”

DECC Eamon Ryan Ireland Offshore Wind
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleMasdar to develop 70MW Côte d’Ivoire solar plant
Next Article Axpo to build Swedish battery storage project

Related News

Industry hails Irish Tonn Nua auction result

November 26, 2025

WindEurope 2025: EirGrid signs offshore MoU

April 9, 2025

Dublin appoints Eirgrid as Irish offshore TSO

May 13, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}