EnBW has gone to market to find a company to undertake the detailed design of foundations for the 900MW He Dreiht offshore wind project in the German North Sea.
The contract scope includes structural design of both jackets and monopiles as well as electrical, mechanical and corrosion protection lay outs.
Advertisement
Work is expected to start from 1 January 2021 and run to 31 December 2025 with an option for an extension for optimisation of the design, the developer said in a tender note.
Bids are due in by 7 May.
He Dreiht will be located about 85km north of the island Borkum and 95km west of the island Helgoland.
The wind farm is to be built as a zero-subsidy scheme and is due online by 2025.