Pin pile installation has begun at Copenhagen Infrastructure Partners’ 495MW Fengmiao 1 offshore wind project off the coast of Taiwan.
The array’s 99 pin piles were manufactured by Taiwan’s Century Huaxin Wind Energy and CTCI MAC, while transportation and installation was carried out by CDWE vessel Green Jade.
Advertisement
The developer said: “CIP continues working closely with supply chain partners, local communities, and government authorities to ensure safe construction, high project quality, and timely delivery-while advancing Fengmiao II Offshore Wind Farm to support Taiwan’s long-term green energy transition.”
The array will feature 33 Vestas V236-15.0 MW turbines.