Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » First five turbines installed at Vineyard Wind
Offshore Wind

First five turbines installed at Vineyard Wind

reNEWS EditorialBy reNEWS EditorialDecember 6, 20232 Mins Read
First five turbines installed at Vineyard Wind

Avangrid and Copenhagen Infrastructure Partners (CIP) are preparing to deliver first power from their 800MW Vineyard Wind project in the US after installing the first five GE Haliade-X turbines.

Once energised in the coming weeks, the site will deliver approximately 65MW of clean energy from the turbines, enough to power 30,000 homes and businesses in Massachusetts.

Advertisement

The power from the first five machines will interconnect to the New England grid in Barnstable, transmitted by underground cables connecting to a substation further inland on Cape Cod.

Before generating first power, Avangrid must complete several critical tests and technical milestones, including final testing of the array and export cables, and energisation of the offshore substation which is one of the largest built in the global offshore industry.

Vineyard Wind 1 remains on track to deliver first power before the end of the year. Once completed, the project will consist of 62 wind turbines to generate 806MW, enough to power more than 400,000 homes and businesses in Massachusetts.

“Our team has worked tremendously hard, through nights, weekends, and holidays to put us in the position to deliver the first power from Avangrid’s nation-leading Vineyard Wind 1 project before the end of the year,” said Avangrid chief executive Pedro Azagra.

“Today, we have fully installed the first five turbines of this historic project, representing a new frontier for climate action and the clean energy revolution in the United States.

“We look forward to working through the final technical requirements and flipping the switch to deliver these first green electrons to 30,000 homes and businesses in Massachusetts, proving that with skill, expertise, and perseverance, the dream of offshore wind in America is real.”

Avangrid CIP Copenhagen Infrastructure Partners Massachusetts Offshore Wind Renewable energy news US USA Vineyard Wind wind farm
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleSouth Fork Wind delivers first power
Next Article DEME eyes Greek offshore wind opportunity

Related News

Orsted, Avangrid and Vineyard bid into New England tender

March 28, 2024

Vineyard Wind signs CTV charter

May 9, 2022

Avangrid Renewables boosts offshore wind team

October 1, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}