CT Offshore has completed the installation of inter-array cables at Dong Energy’s 582MW Gode Wind 1 & 2 offshore wind farm in the German North Sea.
The company said the new purpose built subsea trencher ROV CTO 107 1100 buried all the 97 cables operating at a depth of 100 metres.
CT Offshore chairman Jens Frederik Hansen said: “The cable installation was successfully completed through good team work with the entire project team, including our clients Dong Energy.
“Gode Wind is the largest project to date for CT Offshore and it is a great achievement for our project team.”
Image: monopile foundations at Gode (Dong Energy)