Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » HKZ turbine installation wraps up
Offshore Wind

HKZ turbine installation wraps up

SaraBy SaraJune 13, 20232 Mins Read
HKZ turbine installation wraps up

Almost two years after construction started, the last turbine at Vattenfall’s Hollandse Kust Zuid wind farm has been installed.

Over the next couple of months, the turbines will be commissioned and tested.

Advertisement

Hollandse Kust Zuid is expected to be inaugurated later this year.  

Project Director Ian Bremner said: “We are extremely proud to have reached this milestone.

“The installation of this last turbine is an important moment for the project, not just for us, but also for our partners and all the suppliers and contractors who helped us get here.

“Hollandse Kust Zuid is the first subsidy-free offshore wind farm in the world and we are looking forward to delivering this project.”  

 Cadeler has been supporting Siemens Gamesa with the transportation and installation of all 139 offshore wind turbines using the wind installation vessel, Wind Osprey.

“When we initially planned for this project, it was the first time ever the Siemens Gamesa 11MW turbines were to be installed on a commercial scale.

“This of course required skilful engineering work and a good collaboration with our partners at Siemens Gamesa and Vattenfall.

“We are proud to have played a vital role in the realisation of this impressive and record-breaking wind farm project that will contribute to the green transition,” said Jacob Heinricy Jensen, Chief Operations Officer at Cadeler.  

The total number of turbines is 139 is one less than the 140 that were planned for.

Last year, one of the foundations was damaged after a collision with bulk carrier Julietta D, after it became rudderless during a storm and drifted through the wind farm.

In alignment with partners, contractors and authorities it was decided that the foundation was damaged too much to install a turbine and will not be replaced.

It will be removed in 2024 and it has not been decided yet what will happen with the location once the foundation has been removed. 

HKZ Offshore Wind Vattenfall
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleQ Energy kicks off 320MW renewables buildout in France
Next Article Offshore wind CapEx costs forecast to soar

Related News

Vattenfall cuts the ribbon on 1.5GW HKZ

September 29, 2023

TenneT energises HKZ Alpha grid connection

March 31, 2022

Vattenfall greenlights 1500MW Hollandse Kust Zuid

June 4, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}