PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » New York approves Empire Wind transmission plan
Grid

New York approves Empire Wind transmission plan

Michael Lee-MurphyBy Michael Lee-MurphyFebruary 14, 20251 Min Read
Equinor

The New York State Public Service Commission has approved the construction of an interconnection cable for Equinor’s 816MW Empire Wind 1 project. 

The phase approved involves construction activities within Con Edison’s Gowanus substation property in New York City, including excavation and installation of duct banks, cable pulling, site restoration, and associated decommissioning

Advertisement

Commission Chair Rory Christian said: “Approval of the Environmental Management and Construction Plan (EM&CP) to commence construction of this phase of the Empire Offshore Wind 1 Interconnection Cable Project is an important step.

“The Commission is proud to support the growth of New York’s renewable electricity marketplace.”

The transmission line for the project runs 17.5 miles from the boundary of New York State waters to the point of interconnection in Brooklyn, and will feature two 230-kilvolt (KV) HVAC submarine cables and a 15.1 nautical mile-long export cable corridor. 

There will also be an onshore substation located at the South Brooklyn Marine Terminal that will increase the voltage to 345 kV for the onshore interconnection cables.

Two 345-kV cable circuits, each with three single-core HVAC onshore interconnection cables, will be buried underground from the onshore substation to the point of interconnection at the Gowanus 345-kV substation 

Empire Wind 1 Equinor New York south brooklyn marine terminal
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleEnvision bags 58MW turbine order
Next Article ‘Next German government must back wind energy’

Related News

New York gives Empire Wind the green light

May 17, 2024

GE, Bond to deliver Empire Wind 1 onshore substation

March 22, 2022

Equinor, BP select Vestas 15MW for Empire Wind 1&2

October 18, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}