Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Ofgem outlines Seagreen 1 OFTO licence tender
Offshore Wind

Ofgem outlines Seagreen 1 OFTO licence tender

SaraBy SaraJanuary 20, 20222 Mins Read
Seagreen plants first root off Scotland

Ofgem has officially launched the process to identify a suitable bidder for the offshore transmission licence for the Seagreen Phase 1 offshore wind project off Scotland.

The regulator has made available various documents relating to the TR9 tender.

Advertisement

These include the Enhanced Pre-Qualification document, which sets out the requirements bidders need to demonstrate in order to be invited to participate in the Invitation to Tender (ITT) stage for TR9.

Bidders should demonstrate that they satisfy the requirements set out in this document and demonstrate how they would approach financing, operating and managing offshore transmission assets.

Ofgem will evaluate bidders’ submissions against the criteria published in this document and select a shortlist of qualifying bidders who will be invited to participate in the ITT stage.

Once a preferred bidder is selected there will be an optional Best and Final Offer (BAFO) stage and a preferred bidder stage where the relevant entity is required to demonstrate that it can become the successful bidder.

The BAFO stage may be conducted if two or more qualifying bidders tie with the lowest TRS or two or more qualifying bidders have the lowest TRS and those TRS are within a small percentage of each other, where in such circumstances all qualifying bidders will be invited to submit a BAFO, or Ofgem considers further value can be obtained from the tender exercise and in such circumstances all qualifying bidders will be invited to submit a BAFO.

The selected bidder for the qualifying project will be granted an OFTO Licence, which is expected to include an entitlement to an associated 24-year revenue stream in return for purchasing the transmission assets from the developer of the Seagreen Phase 1 qualifying project and owning, operating and managing them in accordance with the obligations of the OFTO Licence.

The transmission assets for the 1075MW Seagreen Phase 1 to be tendered include offshore and onshore substations and cables connecting the wind farm to the mainland near Carnoustie in Angus.

Offshore Wind Ofgem Seagreen
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleFluence and ReNew form Indian storage venture
Next Article Siemens Gamesa records €309m Q1 loss

Related News

Ofgem shortlists five bidders for OFTO round

March 24, 2026

Beatrice to pay £33m over market rule breach

May 28, 2024

Ofgem shortlists four OFTO asset bidders

July 18, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • JDR Cable Systems Ltd
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}