Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Orsted completes Borssele 1&2 commissioning
Offshore Wind

Orsted completes Borssele 1&2 commissioning

Robin LancasterBy Robin LancasterNovember 27, 20202 Mins Read
Orsted completes Borssele 1&2 commissioning

Orsted has fully commissioned the 752MW Borssele 1&2 offshore wind farm 23km off the coast of the Netherlands.

The project, which features 94 Siemens Gamesa 8MW turbines installed on monopile foundations, is the company’s first offshore wind farm in the country.

Advertisement

Operation and maintenance will be managed from a base at Vlissingen.

Orsted president and chief executive Henrik Poulsen said: “This is an important milestone for the green transformation and for Orsted.

“We’re proud that we’ve commissioned our first offshore wind farm in the Netherlands, who is among the global frontrunners in the energy transition.

“With Borssele 1&2 as the first step, we wish to make a significant contribution to the Dutch transition from fossil to renewable energy.

“We’re proud that we completed this large-scale clean energy project on time and within budget during the Covid-19 pandemic, while maintaining our focus on health and safety.”

Orsted general manager Benelux Steven Engels said: “It’s great that we now can deliver enough green electricity to power one million Dutch households.

“Orsted has delivered what it promised back in 2016, when we won the tender with a ground-breaking bid price.

“Realising the first project of the large-scale offshore wind roll out programme in the Netherlands is an important milestone for the Dutch energy transition.

“I’d like to thank the Dutch national and regional governments and so many other stakeholders who have helped us achieve this result.

“Zeeland has welcomed us with open arms, which provides an excellent starting point for our operations out of Vlissingen for many years to come.

“Moreover, it’s a good basis for future projects around industry decarbonization in the region, such as the renewable hydrogen project that we announced with Yara.”

Borssele 1&2 senior programme director Flemming Thomsen said: “Together with our suppliers, our construction team has successfully installed this wind farm at high quality in less than nine months.

“By introducing additional health and safety measures offshore as well as onshore, we were able to continue construction during a global pandemic.

“We’re grateful and proud of the result delivered and pleased to witness the commissioning of Borssele 1&2.”

Borssele 1&2 Offshore Wind Orsted
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleRovco underwater robot wins innovation gong
Next Article GWEC sets up India branch

Related News

TenneT completes 700MW Borssele Beta

July 30, 2020

Orsted to bid in 700MW Dutch offshore wind sale

April 29, 2020

Borssele Alpha ready for action

September 5, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}