Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Orsted, PGE seek to expand 2.5GW Baltica complex
Offshore Wind

Orsted, PGE seek to expand 2.5GW Baltica complex

reNEWS EditorialBy reNEWS EditorialFebruary 25, 20222 Mins Read
Orsted

Orsted and PGE have applied for seabed acreage adjacent to the 2500GW Baltica offshore wind farm complex off Poland.

The pair submitted an application to the Ministry of Infrastructure earlier this week for the 45.E.1 site on Lawica Slupska, a 17 square km area that is directly adjacent to the Baltica wind farm zone in the Baltic Sea.

Advertisement

The zone is located approximately 32km from the shore.

Orsted head of region continental Europe Rasmus Errboe said: “Together with PGE, we are applying for a seabed lease area, which is relatively small, but is well located to be added to the already developed acreage of 320 square km where we will build the 2.5GW Baltica Offshore Wind Farm, which will be one of the largest offshore wind farms in our global portfolio.”

PGE president of the management board Wojciech Dąbrowski said: “The location we are applying for, complements the acreage of the Baltica Offshore Wind Farm, the largest offshore wind farm being built in the Polish part of the Baltic Sea.

“Over the next five years, we will commission the Baltica 2 and Baltica 3 stages with a total capacity of approximately 2.5GW.

“Obtaining a permit for an area of approximately 17 square km will allow us to achieve synergy with the Baltica 2 project and guarantee maximizing the use of this part of the Baltic Sea, and ultimately will ensure an increase in green electricity production.”

The first stage of the wind farm complex, the 1GW Baltica 3, is planned to become operational in 2026 while the next stage, the 1.5GW Baltica 2, is to be completed by 2027.

Baltica 2 and 3 have location permits, environmental permits, connection agreements to the transmission network with the operator, and have also received an initial Contract for Difference.

PGE said that it expects this year to receive the environmental permit for the transmission infrastructure and will also work on obtaining building permits, which would further mature the project towards final investment decision.

There are currently 11 new lease areas in the Polish part of the Baltic Sea, for which companies can apply for location permits.

Baltica 2 Baltica 3 Offshore Wind Orsted PGE
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticlePort Esbjerg to establish offshore preassembly sites
Next Article Germany puts up 1GW offshore tender

Related News

PGE and Orsted strike key component deals for Baltica 2

July 3, 2023

PGE starts environmental surveys for Baltica 1

September 16, 2022

Orsted, RWE win offshore wind CfDs in Poland

April 8, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}