Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Orsted ploughs ahead with Greater Changhua onshore works
Offshore Wind

Orsted ploughs ahead with Greater Changhua onshore works

SaraBy SaraJune 17, 20202 Mins Read
Heirs take swing at Orsted

Orsted is moving “full speed ahead” with the construction of the onshore works for the 900MW Greater Changhua 1&2a offshore wind complex off Taiwan.

The majority of the onshore civil works for the Greater Changhua onshore substations will be completed by the end of 2020.

Advertisement

The onshore substations will be ready to energise by the end of 2021.

The Danish developer is working with Star Energy Corporation (SEC), a wholly owned subsidiary of engineering, procurement and construction (EPC) contractor Taiwan Cogeneration Corporation, to carry out the works.

Orsted kicked off the construction work of the onshore substations and onshore transmission system for Greater Changhua 1&2a in November 2019.

Star Energy is constructing two onshore substations, cable corridors, and transition joint bays.

Orsted Taiwan general manager Christy Wang said: “Orsted strongly believes that seamless collaboration with local partners is one of the key success factors for excellence in project execution.

“In our partnership, both Orsted and SEC demonstrated our adaptiveness and flexibility.

“Through constant exchanges and learning from each other, we are able to successfully combine our global experience with local expertise to work on the onshore substations and onshore transmission system for the Greater Changhua offshore wind farms.

“Orsted is committed to supporting the development of local supply chains from day one and work with local companies to elevate their capability and QHSE practice to international standards, and potentially enter into the international supply chains in the future.”

Orsted said it continues to share its global best practice with Taiwanese partners, an example of which is the introduction of the ‘rehearsal of concept’ that occurs daily on site.

It enables Orsted and SEC to review progress and go through tasks and safety arrangements for the following day to ensure smooth and safe execution of the installation and construction works, the developer said.

Orsted also hosts archaeological experts on site during excavation works and controls air pollution and noise levels to comply with regulations and standards.

The onshore construction project has created approximately 800 job opportunities, both directly and indirectly, and has “benefited dozens of Taiwanese suppliers” for the substation components and services, including some from Changhua county.

SEC vice president Tom Cheng said: “This is our second offshore wind project. The scope and standards are very different from our previous work.

“The QHSE standards for offshore wind projects are much higher than other construction works in Taiwan.”

Greater Changhua Offshore Wind Orsted
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleNaval Energies, Hitachi Zosen expand floater ties
Next Article Enercon inks 36MW French turbine deal with WPD

Related News

Orsted sells 50% Greater Changhua 4 stake

December 11, 2024

Greater Changhua reaches full operation

April 25, 2024

Greater Changhua 1&2a onshore substations power up

May 4, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}