Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » TenneT ships 900MW DolWin offshore platform
Offshore Wind

TenneT ships 900MW DolWin offshore platform

Eleanore RobinsonBy Eleanore RobinsonAugust 8, 20222 Mins Read
TenneT ships 900MW DolWin offshore platform

TenneT has carried out the sail-out of the 900MW offshore platform DolWin kappa from the Dragados Offshore shipyard in Cádiz, Spain.

The platform consists of a foundation structure (jacket) and a superstructure (topside) and will be installed in the German North Sea. 

Advertisement

The two have a combined height of about 82 metres, so the platform will rise about 53 metres above the surface of the North Sea.

In addition, there will be a bridge that will connect DolWin kappa with DolWin beta (grid connection system DolWin2), which was already commissioned in 2016, in order to efficiently use the already existing infrastructure of the parent platform. 

After three years of construction, the platform is now on board the transport barge Iron Lady and on its way to the Dutch port of Rotterdam.

There, it will be reloaded onto the world’s largest service vessel, the Pioneering Spirit, and then shipped to the installation site.

Once there, DolWin kappa will be installed directly from the work boat.

After the platform is commissioned in 2023, it will convert the alternating current generated by offshore wind farms into direct current, which will then be transmitted to Hilgenriedersiel on the mainland via an approximately 45-kilometre-long subsea cable.

The grid connection system is scheduled to be commissioned in 2023 and provide renewable energy to over 1 million households.

TenneT chief operating officer Tim Meyerjürgens said: “TenneT is taking its mission seriously and advancing the grid expansion in the North Sea step by step.

“With the successful sail-out of the offshore platform DolWin kappa, we have taken the next important leap.

“DolWin6 is already the 13th offshore grid connection in our German portfolio and will bolster Europe’s urgently needed energy independence beginning in 2023.

“We also have our partners to thank for the fact that we are reaching this milestone on schedule.

“Working closely with our contractors Siemens Energy and Dragados Offshore, my colleagues took only three years to build the platform despite the enormous challenges posed by the pandemic.”

DolWin kappa Offshore Wind port of rotterdam Spain Tennet
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleDominion Energy wins 2.6GW Virginia offshore wind approval
Next Article Magnora enters UK solar, storage market

Related News

Dragados to open Spanish yard for TenneT platforms

February 13, 2025

TenneT wraps up DolWin kappa installation

September 5, 2022

TenneT’s DolWin kappa platform arrives in German North Sea

August 22, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}