Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » UPDATE: Dogger developers primed for build surge
Offshore Wind

UPDATE: Dogger developers primed for build surge

Stephen DunneBy Stephen DunneSeptember 20, 20194 Mins Read
Galloper glory for Innogy

Developers of 5GW of offshore wind farms in the Dogger Bank are laying the groundwork to unleash multi-year build campaigns at four projects that have secured support in the third Contracts for Difference round.

Equinor and SSE – joint developers of the 1.2GW Creyke Beck A, 1.2GW Creyke Beck B and 1.2GW Teesside A projects – are planning a final investment decision on their projects in 2020, and looking to bring Creyke Beck A online by 2023.

Advertisement

“Further phases of the Dogger Bank project will be developed thereafter,” the developers said.

NKT is the preferred bidder for the supply and installation of the HVDC export cables for the Creyke Beck A and B projects.

The cable outfit will provide four 175 kilometre lengths of 320kV DC offshore cables for the project and four 32 kilometre spans of onshore wire of the same rating.

The wires will be produced at facilities in Karlskrona, Sweden from 2021 and the first lengths installed from 2021, NKT said.

NKT will install the offshore cables using its vessel Victoria and said the value of the contract was €380mln.

In total, Developers said the three Dogger Bank projects will require a capital investment of £9bn between 2020 and 2026.

SSE will be the lead operator during the project construction phase and Equinor will head up the operations phase of the project.

“The successful bids for the world’s largest offshore wind development represent a game-changer for our offshore wind business,” said Equinor chief executive Eldar Saetre.

“A full-scale development of Dogger Bank will constitute an industrial wind hub in the heart of the North Sea, playing a major role in the UK’s ambitions for offshore wind,” he added.

The developers secured 15-year support at £39.65/MWh, £41.61/MWh and £41.61/MWh for the Dogger Bank Creyke Beck A, Creyke Beck B and Teesside A projects, respectively. 

SSE Renewables managing director Jim Smith said the CfD3 success was built on years of hard-won experience in the industry.

“We are thrilled at the success of our offshore wind projects at Dogger Bank. which combined will be the largest wind farm in the world. Reaching this point has been a culmination of over 10 years of development and it is very exciting to work with Equinor on taking the project forward,” he said.

Innogy is meanwhile preparing to start construction of its 1.4GW Sofia project, also in the Dogger Bank, in 2021 following a final investment decision on the project.

The site lies some 195km off the coast of the UK, covers an area of almost 600 square kilometres and secured supports at £39.65 per megawatt hour.

The developer said design refinement work at the project is ongoing.

Sofia Project Director David Few, who led the project through the auction said teamwork was essential in securing a CfD success.

“It has been a huge team effort with many complexities and I congratulate everyone who has worked so diligently to ensure Sofia’s success as they have all played a role in today’s fantastic achievement,” he said.

“Now we have won a CfD we intend to progress the project through the latter stages of development and design, working closely with our major suppliers, a wide cross section of stakeholders and the local Teesside community.”

Innogy’s director of offshore wind Paul Cowling said the CfD3 results showed offshore wind can play a central role in helping the UK deliver on its net zero 2050 commitment.

“The sector’s foresight has enabled the UK to take the lead globally in the deployment of offshore wind, with this auction confirming that costs are now down to a level well below that of fossil fuel generated electricity,” he said.

CfD3 Equinor Europe Innogy Offshore Wind SSE Renewables UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleScottish islands set to be ‘green powerhouse’
Next Article UPDATE: Google search finds 1.6GW of green PPAs

Related News

SSE, Equinor unleash Dogger Bank build

January 17, 2020

OHT secures Dogger foundations prize

November 27, 2019

ABB, Aibel to deliver Dogger Bank platforms

October 30, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Navantia Seanergies
    Navantia Seanergies
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}