Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » ERG commissions first 50MW at Sandy Knowe wind farm
Onshore Wind

ERG commissions first 50MW at Sandy Knowe wind farm

reNEWS EditorialBy reNEWS EditorialOctober 14, 20221 Min Read
Vestas secures 104MW Brazil project order

ERG has commissioned the first 50MW at its Sandy Knowe wind farm in Dumfries and Galloway in the south of Scotland.

The remaining 36MW will enter service at the site during the first quarter of 2023, and earlier than the timeline set out in ERG’s 2022-2026 business plan.

Advertisement

The wind farm, developed and built internally, will have a total installed capacity of 86.4MW and an overall annual production of over 250GWh at full capacity, equivalent to the needs of about 55,000 households, and avoiding the emission of 106,000 tonnes of CO2 each year.

CEO of ERG Paolo Merli commented: “The group is continuing its path of organic growth in the UK, one of the priority markets for the development objectives in our renewable energy portfolio.

“The start-up of the first batch of the Sandy Knowe wind farm adds to the 70.3MW produced by the Craiggore and Evishagaran wind farms in Northern Ireland, which have been in operation since the beginning of 2022, thus bringing today the installed capacity in the UK to over 120MW.”

Dumfries and Galloway ERG Onshore Wind Renewable energy news Sandy Knowe Sandy Knowe wind farm Scotland UK Wind energy wind farm wind power
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleOctopus Energy JV supports 200th community energy project
Next Article Fresh investment to help develop Danish e-methanol facility

Related News

ERG completes 86MW Sandy Knowe wind farm in Scotland

December 19, 2022

Kazakh mining outfit plans 155MW wind project

August 22, 2022

ERG increases capacity at Scottish wind duo 

November 4, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}