French developer Futuren increased revenues by 8% to €28.1m in the first half of 2016, compared with the same period last year.
The increase was mainly down to the commissioning of a 21 MW wind farm in November 2015, the company said.
In the second quarter of 2016, Futuren started construction of the 18MW Chemin Perré and 13MW Les Monts wind farms in France, which are scheduled to be commissioned in September and December, respectively.
The company expects a total of 31MW to be commissioned by the end of the year, compared with 21MW last year.
At the start of next year, it will begin construction on another 21MW project that will be commissioned in 2018.
In total, Futuren’s pipeline of authorised or under construction projects totals 199MW to be commissioned in the next three years.
The company said its wind farm development and management activity recorded a decrease for the first half of 2016 compared with the same period last year, mainly due to the end of some third party contracts in Germany and France at the end of 2015.
Image: Morgue File