Two PNE Group projects with a total capacity of 24MW were successful in the tender round for onshore wind farms organised by the German Federal Network Agency.
The Gnutz-Ost array with three wind turbines and a total output of 18MW is being built in Schleswig-Holstein.
Advertisement
In Rhineland-Palatinate, the PNE Group will construct the Helenenberg wind farm with one machine and an output of 6MW.
Both sites are scheduled to go into construction or operation next year.
Together with the February and May tenders, nine wind farms of the PNE Group with a total capacity of 141.9MW have been awarded contracts this year.