Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Wartsila bags Oz battery order
Energy Storage

Wartsila bags Oz battery order

SaraBy SaraDecember 5, 20242 Mins Read
Wartsila storage on repeat in South-east Asia

Wartsila has been chosen to deliver one of Australia’s largest energy storage systems, as part of the third stage of Origin’s Eraring battery project in New South Wales.

For this stage of the Eraring battery facility at Origin’s Eraring power station Wartsila will install an additional 700 megawatt hours (MWh) of battery energy storage system (BESS) capacity directly to the Eraring Stage 1 system.

Advertisement

This project continues the successful partnership between Wartsila and Origin, bringing the Eraring facility’s total capacity to 700MW/2800MWh.

This makes it the largest battery project in Australia.

The order was booked in Q4 2024.

“The scale of this project is impressive, delivering the largest total dispatch duration of an operating battery or project under construction in the Southern Hemisphere.

“At 2 800 MWh, when cycled once a day, the Eraring battery will dispatch enough energy to power more than 150 000 New South Wales households annually, helping to firm variable supply from wind and solar,” said Greg Jarvis, Head of Energy Supply and Operations at Origin.

The Eraring battery will connect to Australia’s National Electricity Market (NEM), enhancing energy security and reliability in New South Wales as renewable energy supply increases.

With this extension, the Eraring 1 facility will double the length of time it can store energy.

Stage 1 and 3 will operate in grid-following mode, with the potential to switch operation into grid-forming in the future, providing the capability to supply a variety of system strength and system restart ancillary services.

Stage 2 will operate in grid-forming mode at the time of commercial operation.

Origin selected Wartsila for Stage 1 of the project in 2023 and Stage 2 earlier in 2024.

Completion of Stage 3 is expected alongside Stage 1 at the end of 2025.

Stage 2 is expected to come online in the beginning of 2027.

Energy Storage Wartsila
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleScotland earmarks £150m for offshore wind
Next Article ‘EU failing to reap repowering benefits’

Related News

Wärtsilä to deliver 150MW Oz battery system

October 18, 2024

Wartsila to deliver 460MW Oz battery

April 20, 2023

Origin secures planning for 700MW Oz battery

May 12, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Seaway7
    Seaway7
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}