Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » 800MW Viking Link about to be commissioned
Grid

800MW Viking Link about to be commissioned

Eleanore RobinsonBy Eleanore RobinsonDecember 15, 20233 Mins Read
800MW Viking Link about to be commissioned

The new electricity 800MW Viking Link connection between Denmark and England is to be commissioned on 29 December 2023, developer Energinet has said. 

The full capacity of 1400MW cannot be offered to the electricity market from the start, because the West Jutland high-voltage grid has not yet been developed sufficiently, it added.

Advertisement

The existing electricity grid risks overloading and consumers a supply failure if Viking Link was given a complete freedom from day one, according to the developer. 

Energinet said it is working hard on market and operational measures, which can continuously increase the possibility of even more import and export of power across the North Sea.

When Viking Link was adopted in 2015, it happened at the same time as it was decided to expand the 400kV high-voltage grid in West Jutland from Idomlund by Holstebro in the north to the Danish-German border in the south.

The projects were mutually dependent, Energinet said. 

But subsequently, the expansion of 400kV connections along the West Coast has run into several delays, i.a. due to stricter requirements for environmental approvals.

Therefore, the spades on the new 400kV connections have only just been put in the ground, and therefore they are not finished at the same time that Viking Link can be put into operation.

Klaus Winther, director of system responsibility at Energinet, said: “Because the reinforcements of the high-voltage network in West Jutland are delayed, we have always known that it was a challenge to offer the full capacity of Viking Link to the electricity market from day one, but possible with a number of mitigating measures.

“The existing West Jutland electricity grid is simply not strong enough for all the power that, for example, Danish electricity producers want to send through Viking Link and sell in England, to reach the new connection.”

If the capacity was given completely free, in addition to the risk of overload and threatened security of supply, it would also mean that large amounts of Danish electricity production from wind turbines in particular would have to be stopped for periods, because the electricity could easily be sold to England, but not come through the West Jutland grids on the way over there.

Winther added: “I am aware that electricity producers in particular would have liked to see that we could open for more exports than 800MW from the start, but unfortunately we cannot do that without risking putting the Danes’ security of supply out of control.

“With 800MW released to the electricity market, we are actually pushing the existing electricity grid in West Jutland more than we usually do and are getting closer to the limit of what we can squeeze out of the electricity grid without overloading it – precisely to ensure that as much as possible is available capacity in Viking Link.”

Energinet is working hard on both market and operational measures, which will continuously increase the capacity of Viking Link further.

Expansion of the 400 kV network along the west coast of Jutland will greatly increase the capacity of the western Danish high-voltage network and thus enable full capacity in Viking Link.

The first part of the West Coast connections from the German border to Endrup is scheduled to be put into operation in the first quarter of 2025.

Denmark Energinet England Grid Viking Link
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleVestas picks up 186MW Finnish order from Ilmatar
Next Article RWE wins two German onshore auction deals

Related News

National Grid launches Viking Link

April 18, 2024

1.4GW Viking Link goes online

December 29, 2023

Siemens wins Viking Link converter contract

August 26, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}