Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Integrated UK grid from 2025 ‘extremely challenging’
Grid

Integrated UK grid from 2025 ‘extremely challenging’

Eleanore RobinsonBy Eleanore RobinsonDecember 16, 20202 Mins Read
RE makes for 'happy workers'

National Grid Electricity Systems Operator (ESO) believes using shared transmission to link UK wind farms from 2025 could result in missed 2030 deployment targets of 40GW.

The grid operator found an integrated approach from 2025 could save £6bn (€6.55bn) or 18% in capital and operating expenditure between now and 2050 but would be too complex to bring in in the next five years.

Advertisement

A shared network from 2030 would save less, around £3bn, but is believed to be a more achievable timeline for an integrated network, according to a final report for the first phase of grid operator’s offshore coordination project, which forms part of a wider BEIS review into offshore transmission.

National Grid said it has conducted a new sensitivity analysis on the impact of commencing integration next decade following stakeholder feedback on its earlier report.

The grid operator said it believes delivering integrated grids before 2025 would be “extremely challenging and potentially risk meeting the target of 40GW of offshore wind by 2030”.

New figures show an integrated approach from 2030 would save 8% on the total cost transmission infrastructure between now and 2050 and could facilitate a 30% reduction in the new electricity assets required associated with these offshore connections compared to the status quo.

The reduction in infrastructure could bring significant environmental and social benefits, National Grid said.

“There is therefore a need to deploy innovative and flexible approaches to the connection of offshore wind in the intervening period until a new enduring, integrated, approach is in place,” the report’s authors wrote.

“This would be with the aim that, as much as possible, the benefits of an integrated approach can be captured for consumers and communities without placing the delivery of projects underway and the 2030 offshore wind target at undue risk.”

Vattenfall welcomed the findings of the final report.

“National Grid ESO is right to examine what additional coordination can begin on projects which are in the early planning stages,” said project director for Vattenfall’s 1.8GW Norfolk Vanguard and 1.8GW Norfolk Boreas projects Rob Anderson.

“Further delaying projects which already have agreed grid connections, have entered the planning process and are in the later stages of development presents a serious risk that the UK will not meet the target of installing 40GW of offshore wind by 2030.”

Vattenfall hopes to generate first power from its Norfolk Projects in the late 2020s.

National Grid Offshore Wind UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleEU ‘misses chance’ to prioritise renewables
Next Article US developer unleashes 250MW Nobles 2

Related News

RWE completes Norfolk Offshore Wind Zone acquisition

March 27, 2024

Ofgem to clear UK ‘zombie’ projects

November 13, 2023

Integrated UK offshore grid ‘could save £6bn’

September 30, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}