PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » NESO grid reforms unlock 132GW for 2030
Grid

NESO grid reforms unlock 132GW for 2030

Web EditorBy Web EditorDecember 8, 20254 Mins Read
NESO to apply fee to drive connections queue

NESO has confirmed a new pipeline of shovel-ready projects that will be prioritised for connection to Great Britain’s electricity networks, unlocking 283GW of generation and storage and 99GW of transmission demand.

The operator said the overhaul replaces the first-come, first-served model with a system that advances projects aligned to national energy targets and ready-to-build status.

Advertisement

In total, 132GW of projects are identified as aligned with the delivery of the UK government’s Clean Power 2030 target.

Together with the roughly 111GW of existing generation and storage already connected, these projects will support national targets for secure, clean and affordable energy, the grid agency said.

A further 151GW of projects are identified as needed to meet Britain’s needs by 2035.

“This sends clear signals to those investors and developers with ready-to-go projects, enabling them to get building to serve the future needs of society and the economy,” NESO added.

More than 300GW of projects in the old connections queue will not move forward to the next stage at this time. Some of these projects were not ready or were not aligned to national targets, the system operator said.

This process helps ensure that in the future only what is needed will be built, meaning consumers don’t pay unnecessary costs, NESO stated.

“Transforming the connections process isn’t a silver bullet. Thousands of kilometres of new electricity lines and cables are required to ensure power can be delivered to homes and business, and planning reforms must be implemented to speed up decision-making,” it added.

NESO will begin informing customers today of their status in the new delivery pipeline and Distribution Network Operators will similarly begin informing distribution level connecting customers of their status.

Kayte O’Neill (pictured), chief operating officer at NESO, said: “Transforming the grid connections process is a vital first step in unlocking the capacity needs for a secure, affordable energy transition. These changes will cut grid bottlenecks by prioritising ready-to-build projects, giving certainty about when and where they can connect and unlocking billions in clean energy investment.”

Energy secretary Ed Miliband added: “We inherited a broken system where zombie projects were allowed to hold up grid connections for viable projects that will bring investment, jobs and economic growth. To fix this we embarked on ambitious, once in a generation reforms to clean up the queue and prioritise the projects that are ready to help us deliver clean power by 2030.”

Ofgem chief executive Jonathan Brearley stated: “Together we’ve cleared the gridlock and created a new pipeline that prioritises the projects Britain needs most. We are building grids as fast as the sector possibly can, while ensuring generation gets connected.”

Chris Stark, head of mission control for Clean Power 2030, said: “This overhaul of the connections process is the single most important step we will take towards a clean power system. The energy projects our country needs now have the green light to deploy at a pace we haven’t seen for decades.”

“A key barrier to the investment and deployment of clean power has been the time taken for projects to secure a grid connection. The changes announced today recognise this issue and will help to bring more stable power costs to the public quicker by enabling faster energy network connections.,” said Scottish Renewables chief executive Claire Mack.

“Our grid is a critical UK infrastructure asset and getting it fit for the future, as well connecting projects in the right places at the right time and at as low a cost as possible, is essential to our long-term energy security. Creating the best possible conditions to build and invest in Scotland is paramount for the realisation of our clean power ambitions. We will continue to work with government to optimise the Strategic Spatial Energy Plan and take the measures needed to enhance the viability of Scottish projects for the benefit of the whole country” she added.

Grid NESO shove ready projects transmission demand UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleZelestra to sell Latin America platform
Next Article UK marks 25 years of offshore wind

Related News

NESO extends Gate 2 connections evidence window

July 25, 2025

NESO to ‘pause’ grid connection bids

January 15, 2025

UK government to take control of NGESO

September 13, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Seaway7
    Seaway7
  • Pembroke Port
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}