Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » NESO opens window for new grid connections
Grid

NESO opens window for new grid connections

Stephen DunneBy Stephen DunneJuly 8, 20253 Mins Read
NESO opens window for new grid connections

NESO has opened a three-week evidence window for projects holding a UK grid connection agreement, kicking off a sweeping reordering of Britain’s 738GW connections queue.

The process, launched on 8 July and running until 29 July, marks the first practical step in NESO’s plan to scrap the first-come, first-served system that has allowed unviable and speculative ventures to block ready-to-build wind, solar and storage schemes.

Advertisement

More than 5000 projects must now submit detailed evidence packs to demonstrate construction readiness and strategic value if they wish to keep a near-term place in the queue.

Applications will be assessed against criteria set out in NESO’s connections reform evidence handbook and allocated to one of two streams.

Projects judged shovel-ready and aligned with the government’s Clean Power 2030 ambition will receive confirmed modification offers, including updated energisation dates, site data and reinforcement requirements.

Schemes failing to meet the new bar will be issued provisional deferred offers with no firm connection date. They may re-apply in future biannual windows or withdraw from the process.

Projects that do not file evidence by the deadline will automatically fall into the latter category.

NESO chief operating officer Kayte O’Neill said opening the window was a key moment in the “once-in-a-lifetime transformation” of the electricity network.

“By prioritising agreements for projects that are critical and shovel-ready, developers will get the certainty they need to support investment decisions,” she said.

The operator said the queue has grown tenfold in five years and now totals four times the generation capacity required to meet the 2030 clean-power target.

Only around 170GW of the projects currently seeking access are expected to be needed this decade.

Reforming the queue is central to the government’s Plan for Change, which aims to unlock up to £40bn a year of private investment and double onshore wind capacity alongside rapid deployment of other renewables.

Energy minister Michael Shanks called the evidence window “a milestone in our work to overhaul the connections queue and unleash ready-to-go clean power projects”. He urged developers “to demonstrate that their projects are ready to progress”.

NESO intends to publish the list of successful projects from September and begin issuing revised connection offers in the autumn, starting with schemes due online in 2026–27.

The operator said it aims to have updated contracts in place for every project needed to meet the 2030 target by early next year.

Projects connected at transmission level, and large embedded generators, must submit evidence directly to NESO, while smaller distribution schemes should file through their distribution network operator.

Ofgem deputy director of strategic planning and connections Jack Presley Abbott said the reforms would “cut back red tape and fast-track ready-to-go home-grown clean power projects”, supporting everything from housing and hospitals to EV charging and data centres.

NESO stressed that complete and accurate submissions are essential for a full and fair assessment.

O’Neill said the process would also give confidence to consumers that the power system can deliver clean and stable electricity for the long term.

Connections reform Europe NESO Offshore Wind Ofgem Onshore Wind Solar UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleMcGrail confirmed as permanent GB Energy chief
Next Article Thor offshore substation ready for sail-away

Related News

NESO extends Gate 2 connections evidence window

July 25, 2025

NESO urged to extend grid connections deadline further

July 22, 2025

NESO sets out timeline for connections reform

June 10, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}