Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » WindEurope takes aim at grid bottlenecks
Grid

WindEurope takes aim at grid bottlenecks

reNEWS EditorialBy reNEWS EditorialJuly 5, 20245 Mins Read
EU 'misses chance' to prioritise renewables

Getting access to the electricity grid is now the number one bottleneck to deploying renewables at scale, a new report from industry body WindEurope has found.

It states that across Europe hundreds of gigawatts of wind energy projects have applied for a grid connection permit and are waiting for an answer, adding the resulting queues have led to administrative overload and serious delays in the much-needed expansion of wind energy.

Advertisement

In a new study WindEurope analyses the grid access challenges in Europe and proposes practical, immediate actions to release grid capacity for new and repowered wind farms.

The EU wants to increase its wind energy capacity from 220GW today to 425GW by 2030 and 1300GW by 2050. Wind is key to energy security, affordable electricity and industrial competitiveness, said the trade body.

In its recent revision of the Renewable Energy Directive, the EU agreed important reforms to speed up the expansion of wind, notably by improving and streamlining the permitting procedures for new wind farms. These are already having an impact – in the (small number of) Member States that have implemented the new rules on time.

The new number one bottleneck to the expansion of wind and other renewables is now grids, said WindEurope.

Currently more than 500GW of potential wind energy capacity in France, Germany, Italy, Spain, Poland, Romania, Ireland, Croatia and the UK are waiting for an assessment of their application for a network connection assessment. Italy and the UK each have more than 100GW of projects waiting.

These are the capacities that want a grid connection permit, said WindEurope.

They won’t all be built,” it said.

“Many of the schemes won’t make it through the permitting process. Others will be challenged in court. Some are competing against each other in national auctions, sometimes even for the same site – and only the winning bids will be constructed.

“Some projects might be purely speculative. But national authorities and system operators will still have to assess most of them, leading to long grid connection queues.”

The new EU Grid Action Plan identifies key measures that need to be taken to accelerate the expansion and optimisation of Europe’s electricity grids.

“Grid access is the new permitting – the number one bottleneck to the build-out of wind,” said WindEurope chief executive Giles Dickson (pictured).

“The system is clogged up – and holding back hundreds of gigawatts of wind farms. This means less energy security and higher power prices.

“Some reforms will take time, such as more anticipatory planning. But some things can be improved immediately, notably better management of grid connection queues.”

The new WindEurope report analyses the factors for grid connection delays and shows which countries are particularly impacted. It finds network saturation and inefficient planning are the major reasons, but not the only ones. National grid expansion targets are often not aligned with the 2030 renewables expansion targets set out in the Member States’ National Energy and Climate Plans.

The study concludes to speed up the expansion of electricity grids countries should apply the principle of overriding public interest to the permitting of grid infrastructure – regardless of whether it’s to connect renewables directly or for the broader grid reinforcement of the grid.

“Overriding public interest (OPI) for new wind farms is a success story,” said Dickson.

“Germany and others that use OPI have significantly ramped up their permitting volumes – and done so very quickly. But electricity is useless if there’s no grid to transport it.

“National countries can apply OPI to grids – what are they waiting for?”

Currently grid permitting authorities in most European countries apply the “first come, first served” principle to awarding grid access. This means immature and sometimes purely speculative renewables projects need to be assessed when their request comes in, creating excessive queues and backlogs.

It holds up the more mature and promising projects and increases the administrative burdens on the permitting authorities, said the study.

WindEurope said: “Grid permitting authorities need to move away from ‘first come, first served / treat everybody equally’.

“They should apply filtering and prioritisation criteria to better handle the requests for grid connection. The goal must be to reduce the number of projects in the queue, to sift out immature, speculative bids and to ensure a balanced allocation of grid capacity to all strategic net-zero technologies.

“First come, first served can lead to an unthoughtful allocation of grid capacity and an imbalanced mix of technologically and/or geographically. This can severely intensify grid congestion and renewables curtailment which increases costs.”

Many countries are using filtering criteria already, said the trade body. They include stricter entry criteria to the waiting lists for grid connection assessment, adequate financial commitments to reserve the allocated grid capacity and regular checks that projects are progressing towards key milestones. France, Norway, Spain and the UK have started implementing this “milestone achievement” principle to manage their waiting lists more dynamically and drop the slow-moving or stalled projects.

“Spain, Ireland and Greece are already experimenting with prioritisation criteria,” said WindEurope.

It added: “System integration would be a good thing to prioritise. E.g. once you’ve sifted out the immature projects, give priority to projects co-locating different generation technologies and/or storage and/or projects with advanced grid support capabilities.

“This would make for a more efficient use of the grid connection. It would also incentivise developers to tap into the complementary nature of different energy sources, such as a mix of wind and solar, to maximise the use of available grid capacity.”

Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleCorre, SemperPower partner for Dutch BESS
Next Article Labour win a ‘mandate to deliver clean energy’

Related News

Europe installed 15GW of wind in 2024

January 10, 2025

EU unveils action plan for grids

November 28, 2023

‘Grid upgrades needed for energy transition’

September 5, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}