Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » SSE Renewables launches 1.5GW Coire Glas construction tender
Hydro

SSE Renewables launches 1.5GW Coire Glas construction tender

SaraBy SaraFebruary 3, 20222 Mins Read
SSE Renewables launches 1.5GW Coire Glas construction tender

Hydro construction companies have been invited to submit tenders for construction of SSE Renewables’ proposed 1500MW pumped hydro storage scheme at Coire Glas, in Scotland.

Coire Glas, on the shores of Loch Lochy near Invergarry, would be the first large-scale pumped hydro storage scheme to be built in the United Kingdom for more than 30 years.

Advertisement

The Invitation to Tender (ITT) for the main construction works has attracted global interest.

Six shortlisted bidders, who were selected following an extensive supply chain engagement process in 2021, will submit their first bids in April 2022.

Commencement of the ITT process, which will continue until winter 2023, enables SSE Renewables to plan engagement with businesses across the Lochaber and Highland regions to highlight the local supply chain opportunities the project will bring.

The construction phase of the project is scheduled to commence in spring 2024 and, is expected to support up to 500 jobs.

The tendering process will consist of two stages ahead of a final decision on whether to proceed with construction of the scheme in late 2023.

The return of tenders in April will complete the first stage.

At this point one tenderer will be selected for the mechanical and electrical plant scope and two tenderers for the civil engineering scope. 

The selected tenderers will then progress to stage two, which is planned to run from July 2022 until autumn 2023, during which time extensive ground investigation works will be undertaken across the site.

This work will enable the tenderers to refine their project designs. 

The selection of the preferred civils tenderer, who will work with the chosen mechanical and electrical tenderer to construct Coire Glas on a turnkey basis, is scheduled for autumn 2023.

The six tenderers shortlisted for the main construction works, for the civil engineering scope, are: the Bechtel, Acciona Construcción and Webuild S.p.A consortium, the BAM Nuttall, Eiffage Génie Civil and Marti Tunnel consortium, the Dragados and BeMo Tunnelling UK consortium and STRABAG UK.

For the mechanical and electrical plant scope the tenderers are the ANDRITZ HYDRO and Voith Hydro partnership and GE Hydro France.

Coire Glas Hydro SSE Renewables
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleCIP team plans 240MW electrolyser in Norway
Next Article Irish citizens show big support for renewables

Related News

SSE wins award for hydro project

September 10, 2025

Work starts at SSE Renewables Scottish hydro project

December 14, 2022

SSE reveals Coire Glas hydro tender shortlist

June 1, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}